William Beaumont Hospital - New Addition

Home » Case Studies » William Beaumont Hospital - New Addition


Beaumont Hospital

Energy Efficiency Design Review

Project: Energy Conscious Design Review Program

Client: Beaumont Services Company

Scope: Provided energy efficiency consulting to ensure an energy efficient design of new 650,000-square-foot addition to the hospital. Celtic Energy’s duties included:

  • Review of A/E plans and specifications
  • Recommend design improvements to reduce utility costs
  • Develop savings calculations for recommended measures
  • Interface with A/E design team to integrate energy saving measures into project

Features: Since construction had already begun, recommendations were limited to those that would not cause any delays to the project schedule.  Celtic Energy analyzed the project design and presented a list cost savings measures which easily could be included in the program without any setbacks. The estimated savings from CEI’s recommendations are $120,000.

For a Printable Version, click here.